Mill & Overlay and Crack Repair Projects Approved
During Wednesday night’s meeting, the Board of Trustees approved a construction contract with Brannan Sand and Gravel Company LLC to complete the mill and overlay paving and crack repair projects identified in the 2024 Capital Improvement Projects budget.
The work will include the areas listed below:
Edge mill and overlay:
Monarch Estates
- Sandy Ridge Ave- From Birch St to Barron St
- Bald Eagle St from Sandy Ridge Ave to Monarch Dr
- Silverleaf Ave- From Barron St to Cul-de-sac
- Barron St- From Silverleaf Ave to Cud-de-sac.
- Shenandoah Ave- From Silverleaf Ave to Cul-de-sac
- Bedford St- From Monarch Dr to Cul-de-sac
- Monarch Dr- From Bedford St to Bald Eagle St.
- Bailey St- From Monarch Dr to Cul-de-sac
- Belmont St- From Sandy Ridge Ave to Cul-de-sac
- Autumn St- From Silverleaf Ave to Cul-de-sac
Oak Meadows
- Ulysses Ave- From Oak Meadows Blvd down to and including both Cul-de-sac's
- Oak Meadows Blvd- From Firestone Blvd 400' to Trailway Ave
Crack Repair:
- 300 tons of crack repair will be completed on 2" or larger cracks in the Stone Ridge subdivision.
- 500 tons of crack repair will be completed on 2" or larger cracks in the Monarch Estates subdivision.
- 500 tons of crack repair will be completed on 2" or larger cracks in the Oak Meadows subdivision.
The projects will begin no later than June 1, 2024, weather-dependent, and will be completed within 90 days. As more information is available on the schedule, it will be shared with the community.