Historic Firestone Waterline Project Update

Historic Firestone Waterline & Roadway Replacement Project Update


Update May 7, 2024 - Beginning Wednesday, May 8, 2024, from 8:30 a.m. - 3:00 p.m., water will be shut off to allow for a new water main to be installed. Residents along Florence Avenue impacted received a door hanger yesterday with more information. Representatives from DeFalco Construction and the Town of Firestone will be onsite to answer any questions throughout the day.



Sent April 3, 2024 - Beginning Monday, April 8, 2024, Defalco Construction will begin work on Historic Firestone Waterline and Roadway Replacement Phase 2 - Project #2. 

Work will start on 4th Street, 1st Street, and Florence Court and will move to 2nd Street and 3rd Street, accordingly. The schedule is subject to change and any major changes to the schedule will be shared with the community. Weather permitting, regular work hours will be from 7:00 a.m. to 7:00 p.m. Monday through Friday, and the project should be completed by Fall 2024. 

Residents who will be impacted by the work will receive door hanger notices from the contractor with specific timing for the work on their street.

Motorists are urged to pay close attention while driving through the work area and be prepared for slight delays. While on 4th  Street and 1st Street, be aware that there will be multiple lane shifts at both intersections during construction. Please abide by all posted traffic control signs, reduce speeds in the work zone, and avoid the work area if possible.

For more information on this project, contact Town of Firestone Senior Civil Engineer, Nate Haasis, at 303-531-6274.  